For a PET bottling line purchase, how should lead time, installation/commissioning and wear-part plans be written into the contract?
• Set separate lead times for filler, capper and labeler with clear FOB and arrival dates.
• Installation/commissioning must include dry and product runs; acceptance when capacity beat meets contract.
• Wear-part list covers filling valve seals, star wheels, conveyor belts and grippers with replacement intervals.
• Require two-year spare price list and 48-hour delivery for critical parts.
• Train operators and maintenance staff at least 5 days including CIP/SIP procedures.
• Installation/commissioning must include dry and product runs; acceptance when capacity beat meets contract.
• Wear-part list covers filling valve seals, star wheels, conveyor belts and grippers with replacement intervals.
• Require two-year spare price list and 48-hour delivery for critical parts.
• Train operators and maintenance staff at least 5 days including CIP/SIP procedures.