How to split and control lead time and installation schedule for a twin-screw extruder?
• Gearbox and screw elements are long-lead items, typically 12-16 weeks.
• Barrels and heating/cooling systems can be completed in parallel within 8 weeks.
• Pre-shipment 72-hour continuous load test with torque curve records is mandatory.
• On-site installation includes alignment and utilities hookup; allow 7-10 days commissioning.
• Barrels and heating/cooling systems can be completed in parallel within 8 weeks.
• Pre-shipment 72-hour continuous load test with torque curve records is mandatory.
• On-site installation includes alignment and utilities hookup; allow 7-10 days commissioning.