How to set standard lead time and installation window for a 6-axis robot from PO to production?

📅 Published 2026-09-18👁 1 viewsProduct KnowledgeRobots & Automation📦 工业机器人与自动化
• Standard models ship in 8-12 weeks; custom or special-color units take up to 16 weeks.
• Contract FAT two weeks before shipment and SAT within 10 working days after arrival.
• Installation window needs 7 days foundation curing plus 3 days safety fence erection.
• Set delay penalty at 0.5% of contract value per week, capped at 5%.
• Reserve 5 days for PLC integration and trial production to confirm cycle time.